Eskom has initiated a comprehensive investigation into the cause of an explosion at Matla Power Station in Mpumalanga, which occurred due to the rupture of a high-pressure steam steel pipe. The incident led to significant power disruptions and injuries among the workforce.





On the evening of Thursday, the plant experienced a loud blast owing to the pipe rupture directly above the Unit 6 transformer, leading to immediate power loss in the area. Recovery efforts were hampered by substantial dust and ongoing power issues, delaying a full assessment until daylight on Friday.


As investigators and technical teams continue to examine the site, Eskom’s statement clarified that there is presently no evidence suggesting any foul play. The focus remains on thoroughly understanding the damage's extent and projected timelines for repair and recovery.


This explosion resulted in injuries to nine staff members. According to Eskom, "One [employee] is in critical condition, and two are in semi-critical condition but stable.” Meanwhile, others sustained less severe injuries, with two already discharged from the hospital. The utility has ensured that all affected parties, including uninjured employees and relatives of the injured, receive necessary support and counseling.


The occurrence prompted an immediate response from Eskom executives, including a visit by the Minister of Electricity and Energy, Dr. Kgosientsho Ramokgopa, who offered support to both the leadership at Matla and its employees.


Despite this setback, Eskom reaffirmed that its load shedding suspension, which has reached 261 consecutive days, remains unaltered. The company's proactive approach included taking Unit 5 offline as a safety measure, with its maintenance now rescheduled earlier than planned.


Eskom’s leadership remains resolute in their recovery efforts. Bheki Nxumalo, Eskom’s Group Executive for Generation, emphasized the importance of disciplined investigation to pave the way for the unit's eventual return to service. Reflecting on past improvements, Dan Marokane, Eskom Group Chief Executive, highlighted the pivotal role of Matla Power Station in enhancing energy availability, which has significantly contributed to the current stable load shedding outlook.


The dedicated efforts over the last 18 months have led Matla Power Station to a commendable Energy Availability Factor (EAF) of 67.12%, playing a crucial role in Eskom’s Generation Recovery Plan aimed at ending load shedding altogether.


As the community and Eskom employees rally behind the recovery operations, the future of Matla Power Station hangs in balance, awaiting the detailed outcomes of the ongoing investigations. The incident underscores the critical importance of maintenance and safety protocols in energy generation, especially in aging infrastructure.


Leave a Comment

Rate this article:

Please enter email address.
Looks good!
Please enter your name.
Looks good!
Please enter a message.
Looks good!
Please check re-captcha.
Looks good!
Leave the first review