Picture: for illustration purposes
In a bleak 2023 for South Africa's power infrastructure, Friday marked the nation's 40th day at Stage 6 of load shedding, indicating a problem far surpassing the mere frequency of power cuts. Data from Loadshedding Notifier, a utility app, revealed a striking 19,794 GWh impact of power cuts, higher than the cumulative effects seen in 2015, 2018, 2019, 2020, 2021, and 2022.
Stage 6 load shedding, much more severe than Stages 1 or 4, involves cutting off about 6,000MW of power demand, highlighting why an increase in load shedding frequency and stage is alarming. In previous years, Stage 6 has only been intermittent, while in 2023, it has become alarmingly common.
Electricity Minister Kgosientsho Ramokgopa has had to concede to the public that the nation is set for a season of “intense” load shedding as Eskom prioritises long overdue maintenance. Previous assertions about improved coals fleet generation in summer, curtailing the power cuts, has been proved a joke, with power outputs typically improving in winters due to cooler Lowveld temperatures by the nature of how power stations operate.
The latest report shows a 12.82% of capacity loss due to maintenance, which is double the typical figures for winter. Plants such as Koeberg, whose 900MW unit replacement has overrun its schedule for months, contributed to the increase in breakdowns.
As it grapples with Stage-6 load shedding, Eskom relies heavily on diesel-burning generators, sometimes attaining peaks as high as 1,000MW overnight. Power is also sourced from independent producers such as Avon and Dedisa peaking power plants, and pumped storage schemes, serving to just about fend off a shift to the dreaded Stage 7.
Yet, not all hope is lost. The Kusile’s units are ahead of schedule for repairs, with one unit expected to return to service in the coming month, two months earlier than expected, and it is anticipated to add 720MW to the grid.